A can do a piece of work in 10 days which can be done by B in 12 days. How long would it take to do the work together?
X, Y and Z take 20, 30 and 60 days respectively to complete a job independently. They set out to complete a job together . However Y leaves after 4 days and Z leaves after another 6 days . How many more days will it take for X alone to complete the job now?
X is 25% more efficient than Y and his hourly wages are 25% more. If X is paid Rs.75, how much will Y receive for the same work?